For a safe foundation to perform as desired the ultimate strength of each pile must fulfill both structural and geotechnical limits.
Some pile load tests are a direct method of determining the ultimate geotechnical capacity of a pile. It can be happen with either dynamic test or static test.
The dynamic test is faster than the static test but both methods have the same advantage for evaluating the bearing capacity of the pile.
Another purpose of pile Testing is to insure a sound concrete section of the pile to avoid any probability of failure.
3235 Working Piles Dia 460~770mm, 13~30m Depth (On Two Contracts)
1645 Working Piles Dia 800~1200mm, 18~25m Depth (On Three Contracts)
1388 Working Piles Dia 800~1500mm, 16~18m Depth (On Three Contracts)
92 Driven Piles Dia 900 ~1000mm, 29~31m Depth ( On Two Contracts)
1095 Working Piles Dia 800mm, 23m Depth
1815 Working Piles Dia 800~1250mm, 25~28m Depth